How to reprice a powder coating batch when the masking drawing changes

Calculate the extra masking labor on a revised powder coating print, separate one-time setup and release the right drawing to production.

floo team

TL;DR

When the buyer adds a masking requirement after the quote, count the additional features per part, time one representative part and extend the change across the batch. Record the drawing revision the buyer approved.

  • Identify exactly which surfaces must stay free of coating.
  • Separate additional labor on each part from setup for the batch.
  • Split parts already in process from parts that can still follow the revised print.

Price the change on 80 brackets

Suppose revision B shows two masked holes per bracket. Revision C keeps those holes and adds a masked mating face. The shop has already included the two holes in the base quote. Time the extra work on the new face, including applying and removing the mask and inspecting its edge. Use the shop’s own trial time and quoting rate.

Added operationExample basisChange to the quote
Mask and inspect the new face1.5 extra minutes × 80 brackets120 minutes
Prepare the mask pattern20 minutes once for the batch20 minutes
Labor at a $60 hourly quoting rate140 minutes ÷ 60 × $60$140
Additional consumables$0.25 × 80 brackets$20

The example adds $160 to the batch, or $2 per bracket at this quantity. The 20-minute setup cost belongs to the batch. For one batch of 160 brackets, the same assumptions give $240 of per-part labor, $20 of setup and $40 of consumables, or $300 total.

To repeat the calculation in a spreadsheet, enter quantity in A2, extra minutes per part in B2, one-time setup minutes in C2, hourly quoting rate in D2 and consumables per part in E2. The change amount is =((A2*B2+C2)/60)*D2+A2*E2. With 80, 1.5, 20, 60 and 0.25 in those cells, the result should be 160.

Give the operator an unambiguous release

Mark the face on the revised drawing and ask the buyer to confirm the mask boundary and what passes inspection. Keep a copy of the approved print with the job. A real shop’s guide to masking callouts shows which details an estimator needs from the buyer.

If 12 parts have already been coated under revision B, show those 12 separately on the change request. Get a disposition for them before quoting any rework. Price the remaining 68 using the new operation time. On the traveler, list the affected quantity, drawing revision, approval and first-piece inspection result. At closeout, compare the additional minutes actually used with the minutes quoted.